HT-2023-MAN-000010OpenManchester

Network Plus Services Limited v R&R Civil Engineering Limited

Technology & Construction CourtConstruction (incl construction materials)

4 documents · supplied by the court

Division
TCC
Track
Part 8 Claim
Filed
27 Mar 2023
Last updated
27 Mar 20234 years ago
Parties
2
Documents
4£67.20 for the full file

Parties · 2

Claimant1

Defendant1

Docket · 4

Full file £67.20
  1. Order by Judge - Order for Transfer out

    21 Mar 2023

    Order for Transfer out approved by O'Farrell J - Transferred in from Case HT-2022-000455 in Court Technology and Construction Court

  2. Order by Judge - Order

    3 Feb 2023

    Order TO TRANSFER OUT Approved by O'Farrell J - Transferred in from Case HT-2022-000455 in Court Technology and Construction Court

  3. Filing - Claim Form (Part 8)

    16 Dec 2022

    Claim Form (Part 8)(#) - Transferred in from Case HT-2022-000455 in Court Technology and Construction Court

  4. Filing - Particulars of Claim

    16 Dec 2022

    Particulars of Claim(#) - Transferred in from Case HT-2022-000455 in Court Technology and Construction Court

Cross-references

No related case numbers recorded.