Skip to content
Folio
HT-2021-MAN-000046OpenManchester

Engie Ineo UK Limited v Bannerman Consulting Engineers Limited

Technology & Construction CourtConstruction (incl construction materials)

8 documents · supplied by the court

Division
TCC
Track
Part 7 Claim
Filed
17 Sept 2021
Last updated
25 Jan 20234 years ago
Parties
2
Documents
8£151.20 for the full file

Parties · 2

Claimant1

Defendant1

Docket · 8

Full file £151.20
  1. Order by Circuit Judge - Order

    25 Jan 2023

    Tomlin Order approved by HHJ Davies

  2. Order by Circuit Judge - Order

    21 Feb 2022

    Order HHJ Halliwell 21.2.22 hrg 7.3.22 adj availability by 3.3.22

  3. Order by Circuit Judge - Order

    3 Nov 2021

    Consent Order approved HHJ Davies 2.11.21 CCMC relisted for 7.3.22 stay until 1.3.22

  4. Filing - Reply

    17 Aug 2021

    Reply - Transferred in from Case HT-2021-000170 in Court Technology and Construction Court

  5. Order by Judge - Order

    12 Aug 2021

    Order approved by Jefford J 12th August 2021 - Transferred in from Case HT-2021-000170 in Court Technology and Construction Court

  6. Filing - Defence

    5 Jul 2021

    Defence - Transferred in from Case HT-2021-000170 in Court Technology and Construction Court

  7. Filing - Claim Form (Part 7)

    7 May 2021

    Claim Form (Part 7) (#) - Transferred in from Case HT-2021-000170 in Court Technology and Construction Court

  8. Filing - Particulars of Claim

    7 May 2021

    Particulars of Claim (#) - Transferred in from Case HT-2021-000170 in Court Technology and Construction Court

Cross-references

No related case numbers recorded.

Same firms appear in

Record

Alt case number
—
CE-File instance ID
602974
First collected
29 Aug 2026
Last collected
29 Aug 2026