Skip to content
Folio
HT-2020-000485Open

Horton v Hansen t/a DH Construction

Technology & Construction CourtConstruction (incl construction materials)

11 documents · supplied by the court

Division
TCC
Track
Part 7 Claim
Filed
22 Dec 2020
Last updated
18 Jan 20225 years ago
Parties
4
Documents
11£201.60 for the full file

Parties · 4

Claimant2

Defendant2

  • Hansen t/a DH Construction, KevinLitigant in person
  • Hansen, Kevin Paul RobertLitigant in person

Docket · 11

Full file £201.60
  1. Order by Judge - Order

    18 Jan 2022

    Order by Waksman J Sealed and sent LA 18/1/22

  2. Order by Judge - Order

    4 Jan 2022

    Order - Adam Constable QC

  3. Order by Judge - Order

    20 Oct 2021

    Order - Nicholas Vineall QC

  4. Order by Judge - Order

    14 Sept 2021

    Order by Pepperall J

  5. Order by Judge - Order

    21 Jul 2021

    Order - Veronique Buehrlen QC

  6. Filing - Amended Particulars of Claim

    25 Jun 2021

    Amended Particulars of Claim

  7. Filing - Defence

    28 Mar 2021

    Defence to Reply & Counterclaim of the Clamant# 29-03-2021 01:37 PM Sumaira Pathan

  8. Filing - Reply and Defence to Counterclaim

    17 Feb 2021

    Reply and Defence to Counterclaim

  9. Filing - Defence & Counterclaim

    18 Jan 2021

    Value of Defence & Counterclaim is £9,840.00. A Non-Monetary aspect is absent.#

  10. Filing - Claim Form (Part 7)

    22 Dec 2020

    Claim Form (Part 7)(#)

  11. Filing - Particulars of Claim

    22 Dec 2020

    Particulars of Claim(#)

Cross-references

No related case numbers recorded.

Same firms appear in

Record

Alt case number
CE-File instance ID
533809
First collected
26 Aug 2026
Last collected
26 Aug 2026